Thursday, 11 August 2022 @ 15h00 (CAT) / 14h00 BST / 08h00 (EST) / 07h00 (MDT)

Prevailing macro environment and changing palladium market conditions have prompted a strategic revision of the US PGM operations and expansion plans. Sibanye-Stillwater discusses its prudent plan to defer capital investment on original growth project and re-engineer the operations to protect margins and long-term value.

Programme

Context to the repositioning Neal Froneman
A fresh perspectiveCharles Carter
Technical review  Wayne Robinson
Cost and financial aspectsPieter Henning
Conclusion Neal Froneman

RepositionING for delivery of sustainable value through the commodity cycle

  • Delivered on strategic intent 
  • Return on investment secured – optimising future value for all stakeholders
  • Robust, de-risked plan – greater flexibility
  • Prudent response to changing environment
    • Elevated global inflation 
    • Skills shortage
    • Positioning through the commodity cycles
  • Production growth to 700,000+ 2Eoz by 2027
  • Focus on sustainable cost management – AISC below US$1,000/2Eoz in medium/long term
  • Long life assets with great optionality

*NPV– Reserve Life of Mine model at 30 June 2022 assuming long term pricing of Pd US$1,250/oz, Pt US$1,250/oz and discounted at 6.2%


Sequence of macro economic and operating challenges


Build-up in mined 2E PGM production to 700k+ 2Eoz pa by 2027

East Boulder ~230k 2Eoz pa from 2024

  • Planned hiring, training and supervision of additional miners and geologists supports turnaround in productivity in 2022
  • Production expected to normalise to historical levels by end 2022 and then build to 230koz annual rate
  • Sustain ~ 18 month developed state (ORD)
  • Increased SIB capital
    • Earlier investment in fleet replacement and upgrades to support improved safety technology and the long life production profile
    • ­Current TSF expansion transitions to new waste rock dump, followed by new tailings facility (previously planned post 2030)

Stillwater West ~300k 2Eoz pa from 2027

  • Investment in advanced proximity detection to remove standard operating procedures’ constraints
  • Increased development investment  re-establishes two additional mining fronts beyond Depression zone     & Stillwater Fault
    • Developed state to ~12 months by 2024
    • Greater flexibility drives improved productivity and mining selectivity
  • Increase developed state to ~18 months 

Stillwater East (Blitz) ~170k 2Eoz pa from 2026

  • Temporarily suspend mining in areas that require engineered (cemented) backfill solution until new plant is commissioned (2025 ~3yrs @ US$30m)
    • ~40k 2Eoz  impact in 2022
    • ­Allows for restructuring - cost and  productivity benefits
  • Increase developed state to ~12 months by end 2024
  • Increase developed state to ~18 months in the long term

REPLAY OF LIVE CONFERENCE CALL, ACCESS CODE #42758

South Africa010 500 4108
UK0 203 608 8021
USA1 412 317 0088
Australia073 911 1378
International+27 10 500 4108

Explore More

Integrated Report 2021

Our 2021 reports cover our progress and achievements in delivering on our strategic objectives.

Read More

Innovation and technology

We invest in digitisation and innovative technologies to make the future of mining safer, more efficient and more sustainable.

Read More

Economic impact

We are focused on creating value for all of our stakeholders including driving economic growth wherever we operate.

Read More